The new Whittier Elementary School in Fircrest is on schedule to open in September 2027, according to a Tacoma Public Schools construction update published Nov. 16. Nearly the entire new building is now visible from the street.

Contractors have dried in the upper portion of the new building. That milestone means interior trade work can speed up while framing and exterior enclosure continue across the site, the district said.

Roofing, window installation and weatherization work are all underway.

The gym is next. The district said it will begin to take shape.

The replacement project broke ground May 27. Students and staff have remained in the existing Whittier building while the new school goes up alongside it, according to the district's project page. The existing building is slated for demolition once the new one is finished.

Cornerstone is the contractor. McGranahan PBK designed the new school.

The project is funded by the $535 million school construction bond Tacoma voters approved in 2020.

Families can sign up for construction e-alerts through the district's construction updates page.